Concrete & masonry
How much concrete per square metre?
To work out how much concrete you need per square metre, multiply the area by the thickness and then account for a 5% waste allowance, which results in 9 bags of 20 kg for a 75 mm slab, 12 bags for a 100 mm slab, 15 bags for a 125 mm slab, and 18 bags for a 150 mm slab.
Shopping list
| Item | Buy | Note |
|---|---|---|
| Concrete mix, 20 kg bags | 12 bags | 0.00909 m³ per 20 kg bag (110 × 20 kg bags per m³, scaled by weight) |
| Crushed rock base (50 mm compacted, if used) | 0.12 t | 0.05 m³ compacted |
- Bag yields differ between brands (Boral lists 108 bags of 20 kg per m³, Cement Australia 110). Check the yield on your own bag.
How this was worked out
- Area:
length × width
1 × 1 = 1 m² - Volume:
area × thickness ÷ 1000
1.00 × 100 ÷ 1000 = 0.1 m³ - With waste:
volume × (1 + waste)
0.100 × 1.05 = 0.11 m³ - Bags (20 kg):
volume with waste ÷ yield per bag, rounded up
0.105 ÷ 0.00909 = 11.55 bags - Ready-mix:
volume with waste, rounded up to the order step
0.105 → steps of 0.2 m³ = 0.2 m³ - Base:
area × base depth ÷ 1000 × compacted density
1.00 × 50 ÷ 1000 × 2.4 = 0.12 t
How the concrete volume is calculated
The calculator determines the amount of concrete required by first establishing the surface area in square metres. You multiply the length by the width to find this area. Once the area is known, the volume is calculated by multiplying the area by the thickness and then dividing by 1000. For example, a 1 m² area at 100 mm thickness results in a volume of 0.1 m³. To ensure you have enough material, the calculator applies a 5% allowance for wastage. This is done by multiplying the volume by 1.05. The final bag count is reached by dividing the volume with waste by the yield per bag and rounding up to the nearest whole number. For ready-mix, the volume with waste is rounded up to the nearest 0.2 m³ order step.
Concrete requirements by slab thickness
The amount of concrete needed depends on the depth of the pour. Cement Australia's slab calculator page gives 75 mm as the minimum thickness for a non-load bearing slab and says to consult a professional for loads. At this depth, 1 m² needs 0.08 m³ before waste; with the 5% allowance included (volume × (1 + waste)), that is 9 bags of 20 kg mix. If you increase the thickness to 100 mm, 1 m² needs 0.1 m³ before waste; with the 5% allowance included, that is 12 bags of 20 kg mix. For a 125 mm thickness, 1 m² needs 0.13 m³ before waste; with the 5% allowance included, that is 15 bags of 20 kg mix. At a thickness of 150 mm, 1 m² needs 0.15 m³ before waste; with the 5% allowance included, that is 18 bags of 20 kg mix. In all these instances, the ready-mix order amount is 0.2 m³.
| Thickness | Volume (m³) | Bags (20 kg) | Ready-mix (m³) |
|---|---|---|---|
| 75 mm | 0.08 m³ | 9 bags | 0.2 m³ |
| 100 mm | 0.1 m³ | 12 bags | 0.2 m³ |
| 125 mm | 0.13 m³ | 15 bags | 0.2 m³ |
| 150 mm | 0.15 m³ | 18 bags | 0.2 m³ |
Factors that change the calculation
Several variables influence the final amount of material you need to order. The inputs are the surface area of your project and the depth of the concrete pour. If your area increases, the volume and bag count increase proportionally. The thickness of the slab also changes the answer; for instance, moving from 75 mm to 150 mm doubles the volume required. Additionally, the calculator includes a 5% allowance for wastage, as the Cement Australia slab calculator page does. The yield per bag also affects the count, as different brands provide different results. Boral lists 108 bags of 20 kg per m³, while Cement Australia lists 110 bags of 20 kg per m³. You should check the yield on your specific bag to ensure accuracy.
Base material requirements
When preparing a site for a concrete slab, you may need a crushed rock base. The calculator assumes a base depth of 50 mm. For a 1 m² area, a 50 mm compacted base requires 0.12 t of material. This figure is derived by multiplying the area by the base depth, dividing by 1000, and multiplying by a compacted density of 2.4 t/m³. Australian Native Landscapes gives 2.4 t/m³ as the compacted figure for road base, DGB and FCR. The base figure is the same 0.12 t at every slab thickness in the table, because it depends only on the area and the 50 mm base depth.
Worked example
To understand how the calculator reaches its figures, consider a project with an area of 1 m² and a thickness of 100 mm. First, the area is calculated as 1 m² [length × width; 1 × 1]. Next, the volume is determined as 0.1 m³ [area × thickness ÷ 1000; 1.00 × 100 ÷ 1000]. The calculator then adds the waste allowance to find the volume with waste, which is 0.11 m³ [volume × (1 + waste); 0.100 × 1.05]. To find the number of bags, the volume with waste is divided by the yield per bag of 0.00909, resulting in 11.55 bags [volume with waste ÷ yield per bag, rounded up; 0.105 ÷ 0.00909], which rounds up to 12 bags of 20 kg mix. Finally, the ready-mix is rounded up to the 0.2 m³ order step, resulting in 0.2 m³ [volume with waste, rounded up to the order step; 0.105 → steps of 0.2 m³].
Common mistakes
One common mistake is leaving out the 5% waste allowance; the calculator multiplies the volume by 1.05 before working out bags. Another error is using the wrong yield for 20 kg bags, as Boral and Cement Australia provide different figures per cubic metre. People also sometimes forget to round up the final bag count to the nearest whole number. The calculator rounds ready-mix up to its 0.2 m³ order step, so confirm the order step with your local plant. Finally, ensure you are using the correct units; the calculator uses metres for length and width, and millimetres for thickness. In New Zealand, Dricon (Firth) says its HandiCrete 25 kg bag yields 0.010 m³ and its 40 kg bag yields 0.016 m³; check your product label or supplier for other bags.
Frequently asked questions
What is the minimum thickness for a non-load bearing slab?
Cement Australia's slab calculator page gives 75 mm as the minimum thickness for a non-load bearing slab and says to consult a professional for loads.
How much waste should I allow for?
The calculation includes a 5% allowance for wastage.
What ready-mix order step does the calculator use?
The calculator's starting value is 0.2 m³; confirm with your local plant.
What is the compacted density of road base?
The compacted density for road base, DGB, or FCR is 2.4 t/m³.
How many bags of 20 kg mix are needed per cubic metre?
Boral lists 108 bags per m³, while Cement Australia lists 110 bags per m³.
Sources and assumptions
These are the settings behind every number above. Verified figures link to a source. Editable defaults are common rules of thumb: change them to match your product and your site.
| Setting | Value | Status | Source |
|---|---|---|---|
| concrete bags per m3 20kg cement australia | 110 bags/m3 | Verified 2026-11-18 | Cement Australia Concrete Mix product data sheet (PDS CM rev 3): 110 x 20 kg bags are required per cubic metre. |
| concrete bags per m3 20kg boral | 108 bags/m3 | Verified 2026-11-18 | Boral Concrete Mix product data sheet: 108 x 20 kg bags equate to one cubic metre of mixed concrete. |
| concrete bag yield 25kg | 0.01 m3 | Verified 2026-11-18 | Dricon (Firth) HandiCrete page: 25 kg bag yield 0.010 m3. |
| concrete bag yield 40kg | 0.016 m3 | Verified 2026-11-18 | Dricon (Firth) HandiCrete page: 40 kg bag yield 0.016 m3. |
| concrete slab waste | 5 % | Verified 2026-11-18 | Cement Australia slab calculator page: calculation includes a 5% allowance for wastage and rounds bags up. |
| concrete slab thickness path | 100 mm | Editable default | common practice for paths and patios (Cement Australia how-to uses a 100 mm slab as its example), editable |
| concrete slab min thickness | 75 mm | Verified 2026-11-18 | Cement Australia slab calculator page: minimum thickness for a non-load bearing slab would be 75 mm (consult a professional for loads). |
| concrete readymix order step | 0.2 m3 | Editable default | typical ready-mix ordering granularity, rule of thumb, editable; confirm with local plant |
| concrete readymix consider m3 | 1 m3 | Editable default | Rule of thumb: above about 1 m3 a ready-mix delivery is usually easier than mixing bags. Editable; ask your supplier about minimum orders and short-load fees. |
| concrete base depth | 50 mm | Verified 2026-11-18 | Cement Australia how to lay a concrete slab: excavate an extra 5 cm and compact crusher dust or road base to 5 cm. |
| landscape density roadbase compacted | 2.4 t/m3 | Verified 2026-11-18 | Australian Native Landscapes product weights FAQ: road base/DGB/FCR 2.4 t/m3 (compacted figure). |
| concrete mesh effective length | 5.8 m | Verified 2026-11-18 | InfraBuild ribbed square mesh page: SL72 and SL82 effective area 5.8 x 2.4 m. |
| concrete mesh effective width | 2.4 m | Verified 2026-11-18 | InfraBuild ribbed square mesh page: SL72 and SL82 effective area 5.8 x 2.4 m. |